  1. Topology Exposure & Inventory (TEIV)
    1. TE&IV demo (may be through simulators) - John K
    2. Standalone demo of the TE&IV FW code with the sample schema and models - 28th August 
      1. story around the RAN CNFs and their relations across the deployments
      2. RAN functions (across cloudsite) deployed as CNFs and query their Topography
      3. rApps and Non-RT RiC integration capabilities across the SMO and RIC
    3. 28th Update
      1. Standalone demo is possible, with queries and basic models
      2. will be the internal review with the demo video as a iteration 1 model.
    4. Usecase defined models to be incorporated and showcase the Capabilities once the sample data are available (Stretch)
      1. Topo info is loaded we can showcase of the CNF migration across the subclouds (also at the Geo-Distributed arena)
      2. sync DMS data between Tacker and datastore model (draft version) and show the effects of that on the CNFs - (long run goal)
  2. SMO O2 (FOCOM and NFO (K8s)) demo of the IMS and DMS (as a possibility) - Shashi
    1. 28th Update
      1. Test is in progress for FOCOM in the OAI lab,
      2. NFO is deployed
      3. E2E flow testing - TBD-Stretch for the demo video.
    2. 11th Sept
      1. We will have the mock run in the first week of Oct.
  3. Nephio integration with the OSC-SMO (as a stretch and possible idea for the demo) - Seshu
    1. 28th Update
      1. Nephio integration will start soon after the above task is completed - WIP
    2. 11th Sept
      1. We will have the mock run in the first week of Oct.
  4. Demo on Tacker for DMS ETSi profile. -    Demo ready, thanks 
    1. FM:
      1. Fault mgmt we can have the demo - we will focus on the faults of the Workload and listing them
      2. To have the Tacker being able to handle (core-relate, handle like in control) the faults and manage it (Stretch goal).
    2. PM:
      1. J release code would be used to demo based on Tacker
      2. Client side impl would be required and can be targeted by the demo time.
      3. Review time as 11th Sept.
    3. 14th Update:

      Tacker team is working with to get an env for the demo, WindRiver is one of the possible options.

      Komiyama San is the spoc for the env from WindRiver and work is in progress.

      Need update on the previous video used in the ORAN F2F on FM in Oct 2023, and PM of J release.
      • Kuno San would share the latest videos on FM and PM recorded.
    4. 28th Update:
      • Topology is shared to Bimo by Tacker team
      • Bimo said 2 servers would be available for the demo, as soon as the OS is ready in a couple of days.
      • ORAN-SC INF  based O-Cloud to deploy the Tacker DMS and one server to deploy the SMO (other supporting tools).
        • One server for IMS and ETSi DMS
        • One server for K8s DMS 
        • One VM for the SMO
    5. 11th Sept
      1. End of the Sept 2024 we should be able to  have the demo - Toshi san, Kuno san
      2. 25th Sept 2024 would  be the internal demo day
      3. Bimo env has some connectivity issues, that Tacker team is working on at the moment.
  5. Secure communication between the modules - this is in general between the OSC components. (Stretch Goal across the ORAN-SC modules)
    1. Dmaap - Kafka messaging
    2. Strimzi based comm as an extension to the above one.
    3. this needs to be implemented across the OSC components (like pub-sub)
    4. SMO (O2) DB

...