Updated: 26 March 2020

Risks:

  • E2SM Specification baseline is still not available while the development is being done using draft specifications
  • WLS, FAPI interface files baseline - FAPI interface development is dependent on this
  • UE Attach Scenario development - in medium risk due to the effort needed to complete the development

...

F1-C interface enhancement:  WIPDone

  • Support for following additional F1AP messages:
    • Initial UL RRC Message Transfer
    • UL/DL RRC Message Transfer
    • UE Context Setup Request/Response
  • Enhance F1AP messages:
    • F1AP Setup Request/Response
    • GNB DU Config Update

Basic FAPI messages Implementation - Open

Out of Scope:

  • Use cases – Traffic Steering, Health Check related messages and call flows
  • TDD functionality, NSA
  • End to end testing

...