Agenda:
2024-01-10:
I release status.
OAI integration
J release proposal.
- discuss
2023-12-20:
ORAN NA Plugfest update
...
- O-RAN SMO enhancements - Aarna Networks (Bhanu and Sandeep)
View file name SMO_Upstream_Aarna.xlsx height 250 Problem Statement: While trying to remove the device, the callhome device doesn’t get removed and the mount point that we’re trying to remove is not found.
Impact: Customer will not be able to remove the call home device from SMO
Workaround: None. In the worst case scenario, restarting of the call home device or disconnecting the netconf client will work which may not be a viable option for the customer
RCA: Document Attached
Community JIRA: https://jira.opendaylight.org/browse/NETCONF-989
Community Forum: Attached the image (in ONAP CCSDK)- Continuation to the previous discussion on ONAP SO vs SMO
- Planning to have a discussion on the Nephio R2 F2F meeting - to talk on how these communities can collaborate in the long run
- Operator based, ASD, integration points across these communities and see how can we leverage the functionalities.
- Timo, Seshu and Byung to participate and present the ideas around the topic.
- ONAP E2E orch, Nephio domain and ORAN for the RAN specific workloads as a starting point.
- (Byung) Sana discussed on WG1 Nephio on how the NFVO and other components would interact.
Prev Discussion items -
2023-09-13
ONAP SO vs SMO sync - Byung and Seshu
...
- The placement of the Tacker code needs to be clarified - Toshiaki.
- Update the flow diagram for the homing, inventory and deployment of the NFs using tacker - Toshiaki
- Test case to be used - co-ordinate with Integration team - CSAR package from the prev package - Toshiaki
- Step 1 : A simple app that can be considered as a low lying fruit to validate the flow
- Step 2:
- Possibilities are VNFM Radisys OCU / OAI-OCU for the E2E flow testing once they are ready
- NRT RiC that could be deployed on oCloud.
- The FM data on O2 is available in Nov 2022, on O2 IMS.
- @David Kinsey
- This need to be validated and on the IMS part and DMS needs to be clarification.
- ORAN-SC-INF has already validated the FM data part in their release package.
- PM would be available by March 2024
- @Yuya Kuno : Currently O-RAN WG6 is pending on FM/PM of O2dms, but O2dms of NFV-Profile started to develop FM/PM based on SOL002/SOL003 by Nov train.
2023-08-23 Meeting notes:
Details | Item | Who | Notes |
---|---|---|---|
Recording
View file | ||||
---|---|---|---|---|
|
View file | ||||
---|---|---|---|---|
|
...