§6: We plan with the following sprints (as per Releases):
- Sprint I J release dev sprint 1: AugFeb-21 19 to SepMar-10
- Sprint I J release dev sprint 2: SepMar-11 to OctMar-131
- Sprint I J release dev sprint 3: OctApr-2 1 to OctApr-2221
- Sprint I J release dev sprint 4: OctApr-23 22 to NovMay-12 (last planned development sprint)
- Sprint I J release dev sprint 5: NovMay-13 to DecJun-3 2 (only for unplanned last-minute development items)
- Sprint H I release dev sprint 1: Feb-20´to Mar-12Aug-21 to Sep-10
- Sprint H I release dev sprint 2: MarSep-13 11 to AprOct-21
- Sprint H I release dev sprint 3: AprOct-3 2 to AprOct-2322
- Sprint H I release dev sprint 4: AprOct-24 23 to MayNov-14 12 (last planned development sprint)
- Sprint H I release dev sprint 5: MayNov-15 13 to JunDec-4 3 (only for unplanned last-minute development items)
...
- Filter All RICP items: E release only
- committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-s, subteam-a and all teams.
- committed items only: all teams (committed)
- committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-s, subteam-a and all teams.
- Filter All RICP items: F release only
- committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-s, subteam-utfpr, subteam-p and all teams.
- committed items only: all teams (committed)
- items that are known to require work, but are currently not in F release: link
- committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-s, subteam-utfpr, subteam-p and all teams.
- Filter All RICP items: G release only
- committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-s, subteam-utfpr, subteam-p, subteam-c and all teams.
- committed items only: all teams (committed)
- items that are known to require work, but are currently not in G release: link
- Filter All RICP items: H release only
- committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-p, subteam-s, subteam-utfpr, subteam-c, subteam-ag, subteam-cg
- committed items only: all teams (committed) and all teams (committed + tentative).
- items that are known to require work, but are currently not in H release: link
- committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-p, subteam-s, subteam-utfpr, subteam-c, subteam-ag, subteam-cg
- Filter All RICP items: I release only
- committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-p, subteam-s, subteam-utfpr, subteam-ag, subteam-cg, subteam-r, subteam-gs
- committed items only: all teams (committed) and all teams (committed + tentative).
- items that are known to require work, but are currently not in I release: link
- committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-p, subteam-s, subteam-utfpr, subteam-ag, subteam-cg, subteam-r, subteam-gs
- Filter All RICP items: J release only
- committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-p, subteam-s, subteam-utfpr, subteam-ag, subteam-cg, subteam-r, subteam-gs
- committed items only: all teams (committed) and all teams (committed + tentative).
- items that are known to require work, but are currently not in J release: link
- committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-p, subteam-s, subteam-utfpr, subteam-ag, subteam-cg, subteam-r, subteam-gs
- Filter: All RICP items that are not yet done: all = epics only + non-epics.
- Test Epic and test user story Use RICP test epic RIC-42 and the linked test user story RIC-43 to experiment with JIRA. Right now these are mapped to team/board for team T1: board #16 .
- All Epics (not only RICP): link
- Search for a word in any of the RICP items: link
...