2021-09-07 meeting agenda and minutes
Status update for EPICs in E release
- [INF-193] INF Implement the O2 interface as the MVP
- 5 sub-tasks: no progress
- [INF-173] INF Enable the multiple deployment scenarios
- Added 3 sub-tasks:
- 1 done: AIO-SX
- 1 in-progress: AIO-DX, working on fixing controller-1 installation issues.
- 1 not start: AIO-DX with additional worker nodes
- Added 3 sub-tasks:
- [INF-215] INF support Kubernetes and OpenStack
- Added 7 sub-tasks:
- 4 done
- 3 in-progress
- Upstream Status for meta-starlingx on opendev:
- 144 commits
- 73 merged
- 71 in-review
- Added 7 sub-tasks: