Meeting Info

RIC project meetings are open to the public and held on Tuesdays at 2pm UTC (winter) and 1pm UTC (summer).  World Time Zone Map

Zoom 1 Info:

UTC-timeevery 2nd Tuesday, check from calendar

https://zoom.us/j/9644759813

New York (EDT / UTC-4 during DST (-5 in the winter))every 2nd Tuesday, check from calendar+1 669 900 6833 // +1 646 558 8656 // 855 880 1246 (Toll Free) // 877 369 0926 (Toll Free)
Paris (CEST / UTC+1 in the winter (+2 during DST))every 2nd Tuesday, check from calendar+33 7 5678 4048 // +33 1 8288 0188 // 805 082 588 (Toll Free)
Beijing (CST / UTC+8)every 2nd Tuesday, check from calendar+86 10 87833177 // +86 10 53876330 // 400 616 8835 (Toll Free) // 400 669 9381 (Toll Free)
Tokyo (JST / UTC+9) every 2nd Tuesday, check from calendar+81 524 564 439 // +81 3 4578 1488 // 0 800 100 5040 (Toll Free)
Helsinki  (EEST / UTC+2 in the winter (+3 during DST))every 2nd Tuesday, check from calendar

+358 341092129

Delhi (IST // UTC +5:30every 2nd Tuesday, check from calendarTODO


Other international numbers

World Time Zone Map

International numbers available: https://zoom.us/u/acyy3hylQi

2024-11-26

Recording: meeting recording

  1. NearRT RIC's comparision: RIC_Comparison_Meeting_1.pdf Near-RT RIC Comparison - Draft 1.pdf
  2. 26.11: To organise projetc meeting on mondays as its suitable for most.
    1. 26.11: hw-python and hw-go xapp needs to updated. Last commit is Dec 2022.
    2. 26.11: RIC subscription response is not working between submgr and xapp with hw-go xapp. connection refused error. RMR service name is binding with REST port (8080).
    3. 26.11: RIC subscription response is not working between submgr and xapp with hw-rust xapp. http error code=404,most likley xapp doesn't implement.
    4. 26.11: Jira Issues to be created for b) and c)
    5. 26.11: Need committers for hw xapps, Naman left Samsung and Shubash is busy with other work. Sunil(HCL) to check with his team.
    6. 26.11: Sunil was asking if near Real time RIC support A1 for AI modelling
    7. 12.11: e2sim node fails when trying to send an indication due to ASN.1 sanity check failure
    8. 12.11: RAN_FUNC_ID check fails with latest E2 sim. Explictly needed to export this variable.
    9. 12.11: crictl runtime is not able to pull the image due to tls check in https.
  3. 27.08 : influx 2.x in incompatible with current xapps. NRT RIC installation should install only influx 1.x version. Jira ticket to be raised by Sunil N.08.10: influx2.x works with the xapps, however with e2simulator there is some issue.  Sunil to check.
  4. 12.11: Demo by Ashish Singh (Capgemini) on Conflict Manager
  5. 12.11: Sunil requested for security (IPSec) in RIC PLT. Currently this is not implemented.

2024-11-12

Recording: meeting recording

  1. NearRT RIC's comparision: RIC_Comparison_Meeting_1.pdf Near-RT RIC Comparison - Draft 1.pdf
    1. 12.11: e2sim node fails when trying to send an indication due to ASN.1 sanity check failure
    2. 12.11: RAN_FUNC_ID check fails with latest E2 sim. Explictly needed to export this variable.
    3. 12.11: crictl runtime is not able to pull the image due to tls check in https.
  2. 27.08 : influx 2.x in incompatible with current xapps. NRT RIC installation should install only influx 1.x version. Jira ticket to be raised by Sunil N.08.10: influx2.x works with the xapps, however with e2simulator there is some issue.  Sunil to check.
  3. 12.11: Demo by Ashish Singh (Capgemini) on Conflict Manager
  4. 12.11: Sunil requested for security (IPSec) in RIC PLT. Currently this is not implemented.

2024-10-08

Recording: meeting recording

  1. NearRT RIC's comparision: RIC_Comparison_Meeting_1.pdf Near-RT RIC Comparison - Draft 1.pdf
  2. 27.08 : influx 2.x in incompatible with current xapps. NRT RIC installation should install only influx 1.x version. Jira ticket to be raised by Sunil N.

    08.10: influx2.x works with the xapps, however with e2simulator there is some issue.  Sunil to check.

2024-09-24

No attendees for this day's meeting.

2024-09-10

Recording: meeting recording

  1. Agenda for "K" release :
    • E2 Conflict management between xApps:  Commits raised, to review and merge.  
    • 10.09.2024: Gunja Rastogi confirmed to give a demo on 24.09.2024. The commits are still not merged.
    • scale-in and scale out using K8S operators
    • Enhancements to XApp Rust Framework for Next Release 
    • 10.09.2024: Abhijit's participation is very very limited due to new work.
  2. 27.08 : influx 2.x in incompatible with current xapps. NRT RIC installation should install only influx 1.x version. Jira ticket to be raised by Sunil N.

                      08.10: influx2.x works with the xapps, however with e2simulator there is some issue. 

  1. RICAPP agenda: RICAPP Meetings.

2024-08-27

Recording: meeting recording

  1. Agenda for "K" release :
    1. E2 Conflict management between xApps:  Commits raised, to review and merge.
    2. scale-in and scale out using K8S operators

    3. Enhancements to XApp Rust Framework for Next Release 
  2. 27.08 : influx 2.x in incompatible with current xapps. NRT RIC installation should install only influx 1.x version. Jira ticket to be raised by Sunil N.
  3. RICAPP agenda: RICAPP Meetings.

2024-08-13

Recording: meeting recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Compliant
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2023-12-14 as part of release notes:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-1062 Error while running hw-go and Bouncer xApps 04-06: Sunil to check

    2. RIC-1057 gNB unable to connect during high amount of Subscription Requests - Assigned to Amit Mishra - able to reproduce this issue, some timing issue to reduce to 2s. AbdulWahid to check with Aditya on the 10s timer in E2Manager. 02-07: Review request raised.
    3. RIC-1056 Crashing e2mgr after sending high amount of Subscription Requests - Assigned to Dhiraj
    4. RIC-1055 Unrestricted Registration of RMR Routing Information by xApp
    5. RIC-1054 Kong pod is in crash loopback due to Ingress controller container is not coming up in 1.28 k8s installation- mostly needs kongversion upgrade. Abhijit provided hints.
    6. RIC-1051 Problems with deploying xAPPs for the Near-RT RIC - RELEASE H&I - hwgo is gettong onboarded, still some issues with kpimon-go. 04-06: No issues seen with latest version of xapps.
    7. RIC-1047 crash in E2T metric increment code - WIP- Unable to reproduce the issue. 04-06:possible solution identified. Amit can raise the review issue.
                      02-07: Still unable to reproduce. Will commit the possible solution.
    8. RIC-1045 A1 mediator is in crash loopback state for H-Release And I-Release (HCL team can fix) → DONE (was a mismatch between ric-dep and image versions)
    9. RIC-1044 Potential Missing Array Size Checks Leading to Crashes in e2mgr  - code already committed. Wahid to check with Aditya for merging. 02-07: Followup with Aditya to give +1.
    10. RIC-1043 Crash in E2T buildPrometheusList Function  - WIP - 02-07:  Unable to reproduce the issue.
    11. RIC-1042 Can't register xApp
    12. RIC-1031 Data model is not compliant with latest A1 spec → Naman (02-07: planned to start work in next week, )
    13. RIC-1032 → RIC-1035 - we continue with this under RIC-1035 (discussed with Abhijit in the project meeting) → Thoralf needs to take next step here (see also Abhijit's comment in RIC-1035 and in review)
    14. RIC-1025 memory leak in routing manager
    15. RIC-1017 xapp-frame -  xapp-frame may not be able to successfully subscribe to messages
    16. RIC-1016 e2t sctp_params structure may not be initialized properly → Nokia

    17. RIC-1015 e2t too High default message size. → Nokia

    18. RIC-1014 e2t potential race condition in the `listener` function due to multiple `listener` threads. → Nokia

    19. RIC-1013 e2t e2term pod does not become ready. Possible stack/heap corruption 

    20. RIC-1002 (Nokia fixes) Abnormal signaling process cause E2Term crash (this could be a security issue) → DONE
    21. RIC-1001 CVE-2023-41627 RMR service should verify route tables - Alexandre will take a look (note that this related to unimplemented feature RIC-1007)
    22. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    23. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    24. RIC-915 dms_cli for installing xapp not working (raised by James)
    25. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    26. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    27. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    28. RIC-894 long idle period (days) causes RMR connection breaks
    29. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    30. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    31. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
    32. RIC-837 RMR is not forwarding messages from E2T to E2M
    33. RIC-835 → 2021-12-07 no news from Viktor
    34. fixed: 
  4. James: updates?
    1. 2023-11-21
      1. was at OSC-OAI conference
      2. could start using team accounts to test beds from Colosseum (NU) and ARA
      3. discussed with Bimo (Taiwan lab) on pair-wise testing
      4. discussed with John Keeney (non-rt ric ptl) and discussed A1 pairwise testing. Asked from Sunil what's best A1-policy using xApp. None exists on open-src side. Naman commented that for Policy the hello-world xApp (C++ likely) could be used (just requires RMR  route for policy type (must match the policy type that is created via curl)). James to contact Naman if help needed.
    2. 2024-01-16: TM-500 in Taiwan lab is again available (discussions with Intel on bringing up L1 and L2). RIC probably not one of the very next steps.
    3. 2023-01-30: O-RAN f-2-f: James asked if any demo planned. → not planned.
    4. 2024-02-13: thinking about demos for f-2-f (in discussion with Bimu)
    5. 2024-03-12: No updates. Willing to give demo on ORAN-SC Near RT RIC Demo. Details to be worked on the technical and demo content.
    6. 2024-03-26: Unavailable today.
    7. 2024-04-23:
    8. 2024-05-07: Updated on ORANSC summit. It was well received.
    9. 2024-05-21: No new updates this time.
    10. 2024-07-16: Moved to different group.
  5. Prashant's work in near-RT RIC(subteam-p)
    1. 2023-08-22, 2023-09-26. 2023-11-07: could not participate
    2. 2024-02-13,2024-03-12,2024-03-26,2024-04-09,2024-04-23,2024-05-07, 2024-05-21,2024-07-16: no news
  6. Sunil updates (subteam-h)?
    1. 2023-09-12: can give update next time. Maybe 2 or 3 items to work on.
    2. 2023-11-07: Not in the call today
    3. 2023-11-21: no updates. Difficult to find engineers working on this.
    4. 2024-01-16: demo of xApp project additions in I release → Next time
    5. 2024-01-16: re-evaluating RIC platform Jira items
    6. 2024-01-30: went through old Jira ticket, initial plan for release J: RIC-950, RIC-926, RIC-878 and RIC-860
    7. 2024-02-13: working on RIC subscription delete testing 
    8. 2024-03-12: Implementation completed, facing issues in code submission.
    9. 2024-03-26: Working on RIC-1049, documentation will also be made - Done
    10. 2024-03-09: Absent
    11. 2024-04-23: Not much updates.
    12. 2024-05-07: RIC-1045/RIC-1049 /RIC-1052/RIC-837 are completed. RIC-829 needs code commit.
    13. 2024-05-21:  unavailable
    14. 2024-07-16: Sunil asked on the future spec integrations in RIC side. need to do "K" release planning.
  7. Subhash/Naman updates (subteam-s) ?
    1. 2023-12-05: Naman gave an update on status of Samsung items
    2. 2024-01-16: Naman updated readme (still to merged) on how to deploy RIC using operators.
    3. 2024-01-30, 2024-02-13: no news, but still needs to work on RIC-1031
    4. 2024-03-12: RIC-1031 - Needs more time to complete, To start working on  A1 mediator integration with Non RealTime RIC
    5. 2024-03-26:  Continuing on RIC-1031, Working on RIC-1048 (analysis on RMR scaling, design to be worked upon)
    6. 2024-03-09,2024-04-23,2024-05-07,2024-05-21,2024-06-04: Not available
    7. 2024-07-02: Working on RIC-1027
    8. 2024-07-16: Not present
  8. Abhijit updates (subteam-ag) ?
    1. 2023-10-24:
      1. Abhijit and James release new base image: docker pull nexus3.o-ran-sc.org:10002/o-ran-sc/bldr-ubuntu22-c-go:0.1.0 → still to be made 1.0.0 → Reminder Abhijit Gadgil 
      2. no progress in review on the plain helm chart based deployment in https://gerrit.o-ran-sc.org/r/c/ric-plt/ric-dep/+/11743 → to be merged by Thoralf Czichy 
      3. 1 and 2 of RIC-1004 still be finailized this week. Rest to be moved to a new item.
      4. Sunil asked about the Rust xApp → ready with basic hello world scenario. Documentation is best placed into readme and  confluence.
    2. 2024-01-16, 2024-01-30: No news.
    3. 2024-02-13: continues work on xapp framework rust, incl. metric support
    4. 2024-03-12: No news.
    5. 2024-03-26: Implementation done , testing pending for xapp framework rust, incl. metric support
    6. 2024-03-09: Not available.
    7. 2024-03-23: Interested to work on 1056,1057 in coming weeks, after rust framework is tested. RIC-1006 done, RIC-1007 move to K, RIC-1028- will be taken up next. To give demo on rust-framework 07-05-2024.
    8. 2024-05-07:  RIC-1041 is done. Demo was given for metrics support in xapp-frame-rust that has default RMR Rx/Tx counters.
    9. Video for the demo added.
    10. 2024-05-21,2024-06-04: Unavailable
    11. 2024-07-02: Integration testing of xapp-rust fwk and other issues(feature parity go fwk)
    12. 2024-07-16: unavailable
  9. Cap Gemini updates (subteam-cg)? 
    1. We agreed to come back to repo creation for phase 2 (ricapp part) of conflict manager in 1H2024
    2. 2024-01-16: Ashish presented the  design of conflict manager, first phase: link to slideset
    3. 2024-03-26,2024-03-09,2024-04-23,2024-05-07,2024-05-21,2024-06-04:2024-07-16 unavailable.
  10. Himanshu (subteam-gs) would like to work on RIC-963
    1. 2023-12-05: RIC-963 seems to be ready. Himanshu still wants to test this with unordered IEs. Requires a minor addition in ric-dep repo for new config parameter.
    2. 2024-01-16: RIC-963 ready and merged. New review for RIC-1030 for final changes on checking (or not checking) IE order in additional messages.
    3. 2024-03-12:  Interested work in open issues that are already assigned. To check RIC-1047, if Dhiraj is not working,   length of IE > 1024 in RIC_ACTION_DEFINITION causing some issue. Sandeep is working in it. Issue in submgr. Good to raise JIRA.
    4. 2024-03-26: Assigned RIC-1043,1044,1047. Will provide updates next week.  length of IE > 1024 in RIC_ACTION_DEFINITION causing issue in submgr - Sandeep to check if Jira needs to be raised. RIC-1051- Himanshu looking into it.
    5. 2024-03-09:  No updates on RIC-1043,1044,1047. Amit will contribute to this project.
    6. 2024-04-23: Not present
    7. 2024-05-07: RIC-1044 code committed, to be merged.RIC-1047 WIP, issue not reproducible. Possible issue identified, but need to reproduce. e2sim has some dependency on ubuntu 18.04 version(gcc) Issue to be raised for this also. Another Issue : Himanshu to raise issue related to RIC-1052
    8. 2024-05-21: Issue with e2sim identified and corrected (SIM-117), Issue related to 1052 , additional steps added by Amit and now stands closed.
    9. 2024-07-16: unavailable
  11. Dhiraj:
    1. 2023-12-05: moved the IPv6 item  to J release
    2. 2024-01-16: approval for changes to be committed now obtained. IPv6-related commits expected over the next weeks.
    3. 2024-01-26, 2024-04-09,2024-04-23: no news.
    4. 2024-05-07: Dhiraj not representing Rakuten anymore.
    5. 2024-05-21,2024-06-04: Unavailable
  12. Alexandre (subteam-utfpr)
    1. 2023-08-29: Alexandre working on RIC-989 and RIC-991. Will also take a look at RIC-1001
    2. 2023-09-26: subscription message issue with encoding E2SM parts. A. will send e-mail to Thoralf
    3. 2024-03-12: RIC-989 and RIC-991 closed. RIC-1001 would need support from ric-plt/rtmgr, will send email to Abdulwahid. xapp-frame(C++) changes for xapp registration locally completed. Jira will be raised
    4. 2024-03-26,2024-04-09,2024-04-23: No news.
    5. 2024-05-07: Via mail responded to working on bug fixes in xapp-frame's. xapp-frame-cpp working well, still to make it work on xapp-frame(go) and xapp-frame-py
    6. 2024-05-21,2024-06-04: Unavailable
    7. 2024-07-02: Working on xapp-frame-cpp(changes in subscrition,sdl registrations), current RMR issues take a back seat as they are low prio.
    8. 2024-07-16: unavailable
  13. Nokia (subteam-n)
    1. RIC-997 postponed to J
    2. 2024-02-13: Thoralf leaving Nokia/PTL role. Role is open for applications. Nokia nominated Abdulwahid.
  14. ORAN-SC half day workshop, San Jose, CA on April 29th - Any volunteers to make on-site demo of NEAR RT RIC - James will take it up.
    1. 2024-03-26: New nomination awaited from TOC.
    2. 2024-04-09: The presentation of NEAR RT RIC would be handled by someone else(not James)
    3. “Analysis of Opensource Near-RT RICs – A comparative study”. Mainly, Intern will take the Specs, and analyse the available opensources of Near-RT RICs and prepare a report. I wanted to know your thoughts and interest in mentoring this activity. 
    4. 2024-07-02: Interns from Brazil already workin on it. Preliminary reports are available in Portugese language. This is WIP.
  15. J release
    1. 2024-02-13: Naman's input
      1. no Jira tickets yet, but woudl like to focus on 
        1. K8S operator for day 2 operations, like scale-in and scale-out (but requires some thoughts on messaging) : RIC-1048
    2. I release theme for near-rt RIC was "RIC Platform Enhancements". What's it going to be for J?
      1. Thoralf's proposal based on current Jira list: "Make the platform more robust in handling E2AP, conflicts and A1"
    3. We mark items that you are >90% sure (=”committed”) to work on during 1H2024 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for J release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
      1. committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-p, subteam-s, subteam-utfpr, subteam-ag, subteam-cg, subteam-r, subteam-gs
      2. committed items only: all teams (committed) and all teams (committed + tentative).
      3. items that are known to require work, but are currently not in J release: link,  to include k8s version upgrade, ubuntu OS version, clean up of pending issues.
    1. input for release candidates: leftovers and generally open items, RSAC
    2. Sprint dates
      1. Sprint J release dev sprint 1: Feb-19 to Mar-10
      2. Sprint J release dev sprint 2: Mar-11 to Mar-31
      3. Sprint J release dev sprint 3: Apr-1 to Apr-21
      4. Sprint J release dev sprint 4: Apr-22 to May-12 (last planned development sprint)
      5. Sprint J release dev sprint 5: May-13 to Jun-2 (only for unplanned last-minute development items)
  16. RICAPP agenda: RICAPP Meetings.

2024-07-16

Recording:  zoom meeting

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Compliant
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2023-12-14 as part of release notes:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-1062 Error while running hw-go and Bouncer xApps 04-06: Sunil to check

    2. RIC-1057 gNB unable to connect during high amount of Subscription Requests - Assigned to Amit Mishra - able to reproduce this issue, some timing issue to reduce to 2s. AbdulWahid to check with Aditya on the 10s timer in E2Manager. 02-07: Review request raised.
    3. RIC-1056 Crashing e2mgr after sending high amount of Subscription Requests - Assigned to Dhiraj
    4. RIC-1055 Unrestricted Registration of RMR Routing Information by xApp
    5. RIC-1054 Kong pod is in crash loopback due to Ingress controller container is not coming up in 1.28 k8s installation- mostly needs kongversion upgrade. Abhijit provided hints.
    6. RIC-1051 Problems with deploying xAPPs for the Near-RT RIC - RELEASE H&I - hwgo is gettong onboarded, still some issues with kpimon-go. 04-06: No issues seen with latest version of xapps.
    7. RIC-1047 crash in E2T metric increment code - WIP- Unable to reproduce the issue. 04-06:possible solution identified. Amit can raise the review issue.
                      02-07: Still unable to reproduce. Will commit the possible solution.
    8. RIC-1045 A1 mediator is in crash loopback state for H-Release And I-Release (HCL team can fix) → DONE (was a mismatch between ric-dep and image versions)
    9. RIC-1044 Potential Missing Array Size Checks Leading to Crashes in e2mgr  - code already committed. Wahid to check with Aditya for merging. 02-07: Followup with Aditya to give +1.
    10. RIC-1043 Crash in E2T buildPrometheusList Function  - WIP - 02-07:  Unable to reproduce the issue.
    11. RIC-1042 Can't register xApp
    12. RIC-1031 Data model is not compliant with latest A1 spec → Naman (02-07: planned to start work in next week, )
    13. RIC-1032 → RIC-1035 - we continue with this under RIC-1035 (discussed with Abhijit in the project meeting) → Thoralf needs to take next step here (see also Abhijit's comment in RIC-1035 and in review)
    14. RIC-1025 memory leak in routing manager
    15. RIC-1017 xapp-frame -  xapp-frame may not be able to successfully subscribe to messages
    16. RIC-1016 e2t sctp_params structure may not be initialized properly → Nokia

    17. RIC-1015 e2t too High default message size. → Nokia

    18. RIC-1014 e2t potential race condition in the `listener` function due to multiple `listener` threads. → Nokia

    19. RIC-1013 e2t e2term pod does not become ready. Possible stack/heap corruption 

    20. RIC-1002 (Nokia fixes) Abnormal signaling process cause E2Term crash (this could be a security issue) → DONE
    21. RIC-1001 CVE-2023-41627 RMR service should verify route tables - Alexandre will take a look (note that this related to unimplemented feature RIC-1007)
    22. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    23. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    24. RIC-915 dms_cli for installing xapp not working (raised by James)
    25. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    26. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    27. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    28. RIC-894 long idle period (days) causes RMR connection breaks
    29. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    30. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    31. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
    32. RIC-837 RMR is not forwarding messages from E2T to E2M
    33. RIC-835 → 2021-12-07 no news from Viktor
    34. fixed: 
  4. James: updates?
    1. 2023-11-21
      1. was at OSC-OAI conference
      2. could start using team accounts to test beds from Colosseum (NU) and ARA
      3. discussed with Bimo (Taiwan lab) on pair-wise testing
      4. discussed with John Keeney (non-rt ric ptl) and discussed A1 pairwise testing. Asked from Sunil what's best A1-policy using xApp. None exists on open-src side. Naman commented that for Policy the hello-world xApp (C++ likely) could be used (just requires RMR  route for policy type (must match the policy type that is created via curl)). James to contact Naman if help needed.
    2. 2024-01-16: TM-500 in Taiwan lab is again available (discussions with Intel on bringing up L1 and L2). RIC probably not one of the very next steps.
    3. 2023-01-30: O-RAN f-2-f: James asked if any demo planned. → not planned.
    4. 2024-02-13: thinking about demos for f-2-f (in discussion with Bimu)
    5. 2024-03-12: No updates. Willing to give demo on ORAN-SC Near RT RIC Demo. Details to be worked on the technical and demo content.
    6. 2024-03-26: Unavailable today.
    7. 2024-04-23:
    8. 2024-05-07: Updated on ORANSC summit. It was well received.
    9. 2024-05-21: No new updates this time.
    10. 2024-07-16: Moved to different group.
  5. Prashant's work in near-RT RIC(subteam-p)
    1. 2023-08-22, 2023-09-26. 2023-11-07: could not participate
    2. 2024-02-13,2024-03-12,2024-03-26,2024-04-09,2024-04-23,2024-05-07, 2024-05-21,2024-07-16: no news
  6. Sunil updates (subteam-h)?
    1. 2023-09-12: can give update next time. Maybe 2 or 3 items to work on.
    2. 2023-11-07: Not in the call today
    3. 2023-11-21: no updates. Difficult to find engineers working on this.
    4. 2024-01-16: demo of xApp project additions in I release → Next time
    5. 2024-01-16: re-evaluating RIC platform Jira items
    6. 2024-01-30: went through old Jira ticket, initial plan for release J: RIC-950, RIC-926, RIC-878 and RIC-860
    7. 2024-02-13: working on RIC subscription delete testing 
    8. 2024-03-12: Implementation completed, facing issues in code submission.
    9. 2024-03-26: Working on RIC-1049, documentation will also be made - Done
    10. 2024-03-09: Absent
    11. 2024-04-23: Not much updates.
    12. 2024-05-07: RIC-1045/RIC-1049 /RIC-1052/RIC-837 are completed. RIC-829 needs code commit.
    13. 2024-05-21:  unavailable
    14. 2024-07-16: Sunil asked on the future spec integrations in RIC side. need to do "K" release planning.
  7. Subhash/Naman updates (subteam-s) ?
    1. 2023-12-05: Naman gave an update on status of Samsung items
    2. 2024-01-16: Naman updated readme (still to merged) on how to deploy RIC using operators.
    3. 2024-01-30, 2024-02-13: no news, but still needs to work on RIC-1031
    4. 2024-03-12: RIC-1031 - Needs more time to complete, To start working on  A1 mediator integration with Non RealTime RIC
    5. 2024-03-26:  Continuing on RIC-1031, Working on RIC-1048 (analysis on RMR scaling, design to be worked upon)
    6. 2024-03-09,2024-04-23,2024-05-07,2024-05-21,2024-06-04: Not available
    7. 2024-07-02: Working on RIC-1027
    8. 2024-07-16: Not present
  8. Abhijit updates (subteam-ag) ?
    1. 2023-10-24:
      1. Abhijit and James release new base image: docker pull nexus3.o-ran-sc.org:10002/o-ran-sc/bldr-ubuntu22-c-go:0.1.0 → still to be made 1.0.0 → Reminder Abhijit Gadgil 
      2. no progress in review on the plain helm chart based deployment in https://gerrit.o-ran-sc.org/r/c/ric-plt/ric-dep/+/11743 → to be merged by Thoralf Czichy 
      3. 1 and 2 of RIC-1004 still be finailized this week. Rest to be moved to a new item.
      4. Sunil asked about the Rust xApp → ready with basic hello world scenario. Documentation is best placed into readme and  confluence.
    2. 2024-01-16, 2024-01-30: No news.
    3. 2024-02-13: continues work on xapp framework rust, incl. metric support
    4. 2024-03-12: No news.
    5. 2024-03-26: Implementation done , testing pending for xapp framework rust, incl. metric support
    6. 2024-03-09: Not available.
    7. 2024-03-23: Interested to work on 1056,1057 in coming weeks, after rust framework is tested. RIC-1006 done, RIC-1007 move to K, RIC-1028- will be taken up next. To give demo on rust-framework 07-05-2024.
    8. 2024-05-07:  RIC-1041 is done. Demo was given for metrics support in xapp-frame-rust that has default RMR Rx/Tx counters.
    9. Video for the demo added.
    10. 2024-05-21,2024-06-04: Unavailable
    11. 2024-07-02: Integration testing of xapp-rust fwk and other issues(feature parity go fwk)
    12. 2024-07-16: unavailable
  9. Cap Gemini updates (subteam-cg)? 
    1. We agreed to come back to repo creation for phase 2 (ricapp part) of conflict manager in 1H2024
    2. 2024-01-16: Ashish presented the  design of conflict manager, first phase: link to slideset
    3. 2024-03-26,2024-03-09,2024-04-23,2024-05-07,2024-05-21,2024-06-04:2024-07-16 unavailable.
  10. Himanshu (subteam-gs) would like to work on RIC-963
    1. 2023-12-05: RIC-963 seems to be ready. Himanshu still wants to test this with unordered IEs. Requires a minor addition in ric-dep repo for new config parameter.
    2. 2024-01-16: RIC-963 ready and merged. New review for RIC-1030 for final changes on checking (or not checking) IE order in additional messages.
    3. 2024-03-12:  Interested work in open issues that are already assigned. To check RIC-1047, if Dhiraj is not working,   length of IE > 1024 in RIC_ACTION_DEFINITION causing some issue. Sandeep is working in it. Issue in submgr. Good to raise JIRA.
    4. 2024-03-26: Assigned RIC-1043,1044,1047. Will provide updates next week.  length of IE > 1024 in RIC_ACTION_DEFINITION causing issue in submgr - Sandeep to check if Jira needs to be raised. RIC-1051- Himanshu looking into it.
    5. 2024-03-09:  No updates on RIC-1043,1044,1047. Amit will contribute to this project.
    6. 2024-04-23: Not present
    7. 2024-05-07: RIC-1044 code committed, to be merged.RIC-1047 WIP, issue not reproducible. Possible issue identified, but need to reproduce. e2sim has some dependency on ubuntu 18.04 version(gcc) Issue to be raised for this also. Another Issue : Himanshu to raise issue related to RIC-1052
    8. 2024-05-21: Issue with e2sim identified and corrected (SIM-117), Issue related to 1052 , additional steps added by Amit and now stands closed.
    9. 2024-07-16: unavailable
  11. Dhiraj:
    1. 2023-12-05: moved the IPv6 item  to J release
    2. 2024-01-16: approval for changes to be committed now obtained. IPv6-related commits expected over the next weeks.
    3. 2024-01-26, 2024-04-09,2024-04-23: no news.
    4. 2024-05-07: Dhiraj not representing Rakuten anymore.
    5. 2024-05-21,2024-06-04: Unavailable
  12. Alexandre (subteam-utfpr)
    1. 2023-08-29: Alexandre working on RIC-989 and RIC-991. Will also take a look at RIC-1001
    2. 2023-09-26: subscription message issue with encoding E2SM parts. A. will send e-mail to Thoralf
    3. 2024-03-12: RIC-989 and RIC-991 closed. RIC-1001 would need support from ric-plt/rtmgr, will send email to Abdulwahid. xapp-frame(C++) changes for xapp registration locally completed. Jira will be raised
    4. 2024-03-26,2024-04-09,2024-04-23: No news.
    5. 2024-05-07: Via mail responded to working on bug fixes in xapp-frame's. xapp-frame-cpp working well, still to make it work on xapp-frame(go) and xapp-frame-py
    6. 2024-05-21,2024-06-04: Unavailable
    7. 2024-07-02: Working on xapp-frame-cpp(changes in subscrition,sdl registrations), current RMR issues take a back seat as they are low prio.
    8. 2024-07-16: unavailable
  13. Nokia (subteam-n)
    1. RIC-997 postponed to J
    2. 2024-02-13: Thoralf leaving Nokia/PTL role. Role is open for applications. Nokia nominated Abdulwahid.
  14. ORAN-SC half day workshop, San Jose, CA on April 29th - Any volunteers to make on-site demo of NEAR RT RIC - James will take it up.
    1. 2024-03-26: New nomination awaited from TOC.
    2. 2024-04-09: The presentation of NEAR RT RIC would be handled by someone else(not James)
    3. “Analysis of Opensource Near-RT RICs – A comparative study”. Mainly, Intern will take the Specs, and analyse the available opensources of Near-RT RICs and prepare a report. I wanted to know your thoughts and interest in mentoring this activity. 
    4. 2024-07-02: Interns from Brazil already workin on it. Preliminary reports are available in Portugese language. This is WIP.
  15. J release
    1. 2024-02-13: Naman's input
      1. no Jira tickets yet, but woudl like to focus on 
        1. K8S operator for day 2 operations, like scale-in and scale-out (but requires some thoughts on messaging) : RIC-1048
    2. I release theme for near-rt RIC was "RIC Platform Enhancements". What's it going to be for J?
      1. Thoralf's proposal based on current Jira list: "Make the platform more robust in handling E2AP, conflicts and A1"
    3. We mark items that you are >90% sure (=”committed”) to work on during 1H2024 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for J release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
      1. committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-p, subteam-s, subteam-utfpr, subteam-ag, subteam-cg, subteam-r, subteam-gs
      2. committed items only: all teams (committed) and all teams (committed + tentative).
      3. items that are known to require work, but are currently not in J release: link,  to include k8s version upgrade, ubuntu OS version, clean up of pending issues.
    1. input for release candidates: leftovers and generally open items, RSAC
    2. Sprint dates
      1. Sprint J release dev sprint 1: Feb-19 to Mar-10
      2. Sprint J release dev sprint 2: Mar-11 to Mar-31
      3. Sprint J release dev sprint 3: Apr-1 to Apr-21
      4. Sprint J release dev sprint 4: Apr-22 to May-12 (last planned development sprint)
      5. Sprint J release dev sprint 5: May-13 to Jun-2 (only for unplanned last-minute development items)
  16. RICAPP agenda: RICAPP Meetings.

2024-07-02

Recording:  zoom meeting

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Compliant
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2023-12-14 as part of release notes:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-1062 Error while running hw-go and Bouncer xApps 04-06: Sunil to check

    2. RIC-1057 gNB unable to connect during high amount of Subscription Requests - Assigned to Amit Mishra - able to reproduce this issue, some timing issue to reduce to 2s. AbdulWahid to check with Aditya on the 10s timer in E2Manager. 02-07: Review request raised.
    3. RIC-1056 Crashing e2mgr after sending high amount of Subscription Requests - Assigned to Dhiraj
    4. RIC-1055 Unrestricted Registration of RMR Routing Information by xApp
    5. RIC-1054 Kong pod is in crash loopback due to Ingress controller container is not coming up in 1.28 k8s installation- mostly needs kongversion upgrade. Abhijit provided hints.
    6. RIC-1051 Problems with deploying xAPPs for the Near-RT RIC - RELEASE H&I - hwgo is gettong onboarded, still some issues with kpimon-go. 04-06: No issues seen with latest version of xapps.
    7. RIC-1047 crash in E2T metric increment code - WIP- Unable to reproduce the issue. 04-06:possible solution identified. Amit can raise the review issue.
                      02-07: Still unable to reproduce. Will commit the possible solution.
    8. RIC-1045 A1 mediator is in crash loopback state for H-Release And I-Release (HCL team can fix) → DONE (was a mismatch between ric-dep and image versions)
    9. RIC-1044 Potential Missing Array Size Checks Leading to Crashes in e2mgr  - code already committed. Wahid to check with Aditya for merging. 02-07: Followup with Aditya to give +1.
    10. RIC-1043 Crash in E2T buildPrometheusList Function  - WIP - 02-07:  Unable to reproduce the issue.
    11. RIC-1042 Can't register xApp
    12. RIC-1031 Data model is not compliant with latest A1 spec → Naman (02-07: planned to start work in next week, )
    13. RIC-1032 → RIC-1035 - we continue with this under RIC-1035 (discussed with Abhijit in the project meeting) → Thoralf needs to take next step here (see also Abhijit's comment in RIC-1035 and in review)
    14. RIC-1025 memory leak in routing manager
    15. RIC-1017 xapp-frame -  xapp-frame may not be able to successfully subscribe to messages
    16. RIC-1016 e2t sctp_params structure may not be initialized properly → Nokia

    17. RIC-1015 e2t too High default message size. → Nokia

    18. RIC-1014 e2t potential race condition in the `listener` function due to multiple `listener` threads. → Nokia

    19. RIC-1013 e2t e2term pod does not become ready. Possible stack/heap corruption 

    20. RIC-1002 (Nokia fixes) Abnormal signaling process cause E2Term crash (this could be a security issue) → DONE
    21. RIC-1001 CVE-2023-41627 RMR service should verify route tables - Alexandre will take a look (note that this related to unimplemented feature RIC-1007)
    22. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    23. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    24. RIC-915 dms_cli for installing xapp not working (raised by James)
    25. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    26. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    27. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    28. RIC-894 long idle period (days) causes RMR connection breaks
    29. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    30. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    31. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
    32. RIC-837 RMR is not forwarding messages from E2T to E2M
    33. RIC-835 → 2021-12-07 no news from Viktor
    34. fixed: 
  4. James: updates?
    1. 2023-11-21
      1. was at OSC-OAI conference
      2. could start using team accounts to test beds from Colosseum (NU) and ARA
      3. discussed with Bimo (Taiwan lab) on pair-wise testing
      4. discussed with John Keeney (non-rt ric ptl) and discussed A1 pairwise testing. Asked from Sunil what's best A1-policy using xApp. None exists on open-src side. Naman commented that for Policy the hello-world xApp (C++ likely) could be used (just requires RMR  route for policy type (must match the policy type that is created via curl)). James to contact Naman if help needed.
    2. 2024-01-16: TM-500 in Taiwan lab is again available (discussions with Intel on bringing up L1 and L2). RIC probably not one of the very next steps.
    3. 2023-01-30: O-RAN f-2-f: James asked if any demo planned. → not planned.
    4. 2024-02-13: thinking about demos for f-2-f (in discussion with Bimu)
    5. 2024-03-12: No updates. Willing to give demo on ORAN-SC Near RT RIC Demo. Details to be worked on the technical and demo content.
    6. 2024-03-26: Unavailable today.
    7. 2024-04-23:
    8. 2024-05-07: Updated on ORANSC summit. It was well received.
    9. 2024-05-21: No new updates this time.
  5. Prashant's work in near-RT RIC(subteam-p)
    1. 2023-08-22, 2023-09-26. 2023-11-07: could not participate
    2. 2024-02-13,2024-03-12,2024-03-26,2024-04-09,2024-04-23,2024-05-07, 2024-05-21: no news
  6. Sunil updates (subteam-h)?
    1. 2023-09-12: can give update next time. Maybe 2 or 3 items to work on.
    2. 2023-11-07: Not in the call today
    3. 2023-11-21: no updates. Difficult to find engineers working on this.
    4. 2024-01-16: demo of xApp project additions in I release → Next time
    5. 2024-01-16: re-evaluating RIC platform Jira items
    6. 2024-01-30: went through old Jira ticket, initial plan for release J: RIC-950, RIC-926, RIC-878 and RIC-860
    7. 2024-02-13: working on RIC subscription delete testing 
    8. 2024-03-12: Implementation completed, facing issues in code submission.
    9. 2024-03-26: Working on RIC-1049, documentation will also be made - Done
    10. 2024-03-09: Absent
    11. 2024-04-23: Not much updates.
    12. 2024-05-07: RIC-1045/RIC-1049 /RIC-1052/RIC-837 are completed. RIC-829 needs code commit.
    13. 2024-05-21:  unavailable
  7. Subhash/Naman updates (subteam-s) ?
    1. 2023-12-05: Naman gave an update on status of Samsung items
    2. 2024-01-16: Naman updated readme (still to merged) on how to deploy RIC using operators.
    3. 2024-01-30, 2024-02-13: no news, but still needs to work on RIC-1031
    4. 2024-03-12: RIC-1031 - Needs more time to complete, To start working on  A1 mediator integration with Non RealTime RIC
    5. 2024-03-26:  Continuing on RIC-1031, Working on RIC-1048 (analysis on RMR scaling, design to be worked upon)
    6. 2024-03-09,2024-04-23,2024-05-07,2024-05-21,2024-06-04: Not available
    7. 2024-07-02: Working on RIC-1027
  8. Abhijit updates (subteam-ag) ?
    1. 2023-10-24:
      1. Abhijit and James release new base image: docker pull nexus3.o-ran-sc.org:10002/o-ran-sc/bldr-ubuntu22-c-go:0.1.0 → still to be made 1.0.0 → Reminder Abhijit Gadgil 
      2. no progress in review on the plain helm chart based deployment in https://gerrit.o-ran-sc.org/r/c/ric-plt/ric-dep/+/11743 → to be merged by Thoralf Czichy 
      3. 1 and 2 of RIC-1004 still be finailized this week. Rest to be moved to a new item.
      4. Sunil asked about the Rust xApp → ready with basic hello world scenario. Documentation is best placed into readme and  confluence.
    2. 2024-01-16, 2024-01-30: No news.
    3. 2024-02-13: continues work on xapp framework rust, incl. metric support
    4. 2024-03-12: No news.
    5. 2024-03-26: Implementation done , testing pending for xapp framework rust, incl. metric support
    6. 2024-03-09: Not available.
    7. 2024-03-23: Interested to work on 1056,1057 in coming weeks, after rust framework is tested. RIC-1006 done, RIC-1007 move to K, RIC-1028- will be taken up next. To give demo on rust-framework 07-05-2024.
    8. 2024-05-07:  RIC-1041 is done. Demo was given for metrics support in xapp-frame-rust that has default RMR Rx/Tx counters.
    9. Video for the demo added.
    10. 2024-05-21,2024-06-04: Unavailable
    11. 2024-07-02: Integration testing of xapp-rust fwk and other issues(feature parity go fwk)
  9. Cap Gemini updates (subteam-cg)? 
    1. We agreed to come back to repo creation for phase 2 (ricapp part) of conflict manager in 1H2024
    2. 2024-01-16: Ashish presented the  design of conflict manager, first phase: link to slideset
    3. 2024-03-26,2024-03-09,2024-04-23,2024-05-07,2024-05-21,2024-06-04: unavailable.
  10. Himanshu (subteam-gs) would like to work on RIC-963
    1. 2023-12-05: RIC-963 seems to be ready. Himanshu still wants to test this with unordered IEs. Requires a minor addition in ric-dep repo for new config parameter.
    2. 2024-01-16: RIC-963 ready and merged. New review for RIC-1030 for final changes on checking (or not checking) IE order in additional messages.
    3. 2024-03-12:  Interested work in open issues that are already assigned. To check RIC-1047, if Dhiraj is not working,   length of IE > 1024 in RIC_ACTION_DEFINITION causing some issue. Sandeep is working in it. Issue in submgr. Good to raise JIRA.
    4. 2024-03-26: Assigned RIC-1043,1044,1047. Will provide updates next week.  length of IE > 1024 in RIC_ACTION_DEFINITION causing issue in submgr - Sandeep to check if Jira needs to be raised. RIC-1051- Himanshu looking into it.
    5. 2024-03-09:  No updates on RIC-1043,1044,1047. Amit will contribute to this project.
    6. 2024-04-23: Not present
    7. 2024-05-07: RIC-1044 code committed, to be merged.RIC-1047 WIP, issue not reproducible. Possible issue identified, but need to reproduce. e2sim has some dependency on ubuntu 18.04 version(gcc) Issue to be raised for this also. Another Issue : Himanshu to raise issue related to RIC-1052
    8. 2024-05-21: Issue with e2sim identified and corrected (SIM-117), Issue related to 1052 , additional steps added by Amit and now stands closed.
  11. Dhiraj:
    1. 2023-12-05: moved the IPv6 item  to J release
    2. 2024-01-16: approval for changes to be committed now obtained. IPv6-related commits expected over the next weeks.
    3. 2024-01-26, 2024-04-09,2024-04-23: no news.
    4. 2024-05-07: Dhiraj not representing Rakuten anymore.
    5. 2024-05-21,2024-06-04: Unavailable
  12. Alexandre (subteam-utfpr)
    1. 2023-08-29: Alexandre working on RIC-989 and RIC-991. Will also take a look at RIC-1001
    2. 2023-09-26: subscription message issue with encoding E2SM parts. A. will send e-mail to Thoralf
    3. 2024-03-12: RIC-989 and RIC-991 closed. RIC-1001 would need support from ric-plt/rtmgr, will send email to Abdulwahid. xapp-frame(C++) changes for xapp registration locally completed. Jira will be raised
    4. 2024-03-26,2024-04-09,2024-04-23: No news.
    5. 2024-05-07: Via mail responded to working on bug fixes in xapp-frame's. xapp-frame-cpp working well, still to make it work on xapp-frame(go) and xapp-frame-py
    6. 2024-05-21,2024-06-04: Unavailable
    7. 2024-07-02: Working on xapp-frame-cpp(changes in subscrition,sdl registrations), current RMR issues take a back seat as they are low prio.
  13. Nokia (subteam-n)
    1. RIC-997 postponed to J
    2. 2024-02-13: Thoralf leaving Nokia/PTL role. Role is open for applications. Nokia nominated Abdulwahid.
  14. ORAN-SC half day workshop, San Jose, CA on April 29th - Any volunteers to make on-site demo of NEAR RT RIC - James will take it up.
    1. 2024-03-26: New nomination awaited from TOC.
    2. 2024-04-09: The presentation of NEAR RT RIC would be handled by someone else(not James)
    3. “Analysis of Opensource Near-RT RICs – A comparative study”. Mainly, Intern will take the Specs, and analyse the available opensources of Near-RT RICs and prepare a report. I wanted to know your thoughts and interest in mentoring this activity. 
    4. 2024-07-02: Interns from Brazil already workin on it. Preliminary reports are available in Portugese language. This is WIP.
  15. J release
    1. 2024-02-13: Naman's input
      1. no Jira tickets yet, but woudl like to focus on 
        1. K8S operator for day 2 operations, like scale-in and scale-out (but requires some thoughts on messaging) : RIC-1048
    2. I release theme for near-rt RIC was "RIC Platform Enhancements". What's it going to be for J?
      1. Thoralf's proposal based on current Jira list: "Make the platform more robust in handling E2AP, conflicts and A1"
    3. We mark items that you are >90% sure (=”committed”) to work on during 1H2024 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for J release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
      1. committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-p, subteam-s, subteam-utfpr, subteam-ag, subteam-cg, subteam-r, subteam-gs
      2. committed items only: all teams (committed) and all teams (committed + tentative).
      3. items that are known to require work, but are currently not in J release: link,  to include k8s version upgrade, ubuntu OS version, clean up of pending issues.
    1. input for release candidates: leftovers and generally open items, RSAC
    2. Sprint dates
      1. Sprint J release dev sprint 1: Feb-19 to Mar-10
      2. Sprint J release dev sprint 2: Mar-11 to Mar-31
      3. Sprint J release dev sprint 3: Apr-1 to Apr-21
      4. Sprint J release dev sprint 4: Apr-22 to May-12 (last planned development sprint)
      5. Sprint J release dev sprint 5: May-13 to Jun-2 (only for unplanned last-minute development items)
  16. RICAPP agenda: RICAPP Meetings.

2024-06-04

Recording:  zoom meeting

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Compliant
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2023-12-14 as part of release notes:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-1062 Error while running hw-go and Bouncer xApps 04-06: Sunil to check

    2. RIC-1057 gNB unable to connect during high amount of Subscription Requests - Assigned to Amit Mishra - able to reproduce this issue, some timing issue to reduce to 2s. AbdulWahid to check with Aditya on the 10s timer in E2Manager.
    3. RIC-1056 Crashing e2mgr after sending high amount of Subscription Requests - Assigned to Dhiraj
    4. RIC-1055 Unrestricted Registration of RMR Routing Information by xApp
    5. RIC-1054 Kong pod is in crash loopback due to Ingress controller container is not coming up in 1.28 k8s installation- mostly needs kongversion upgrade. Abhijit provided hints.
    6. RIC-1051 Problems with deploying xAPPs for the Near-RT RIC - RELEASE H&I - hwgo is gettong onboarded, still some issues with kpimon-go. 04-06: No issues seen with latest version of xapps.
    7. RIC-1047 crash in E2T metric increment code - WIP- Unable to reproduce the issue. 04-06:possible solution identified. Amit can raise the review issue ??
    8. RIC-1045 A1 mediator is in crash loopback state for H-Release And I-Release (HCL team can fix) → DONE (was a mismatch between ric-dep and image versions)
    9. RIC-1044 Potential Missing Array Size Checks Leading to Crashes in e2mgr  - code already committed. Wahid to check with Aditya for merging.
    10. RIC-1043 Crash in E2T buildPrometheusList Function  - WIP - Unable to reproduce the issue.
    11. RIC-1042 Can't register xApp
    12. RIC-1031 Data model is not compliant with latest A1 spec → Naman (planned to start work in next week)
    13. RIC-1032 → RIC-1035 - we continue with this under RIC-1035 (discussed with Abhijit in the project meeting) → Thoralf needs to take next step here (see also Abhijit's comment in RIC-1035 and in review)
    14. RIC-1025 memory leak in routing manager
    15. RIC-1017 xapp-frame -  xapp-frame may not be able to successfully subscribe to messages
    16. RIC-1016 e2t sctp_params structure may not be initialized properly → Nokia

    17. RIC-1015 e2t too High default message size. → Nokia

    18. RIC-1014 e2t potential race condition in the `listener` function due to multiple `listener` threads. → Nokia

    19. RIC-1013 e2t e2term pod does not become ready. Possible stack/heap corruption 

    20. RIC-1002 (Nokia fixes) Abnormal signaling process cause E2Term crash (this could be a security issue) → DONE
    21. RIC-1001 CVE-2023-41627 RMR service should verify route tables - Alexandre will take a look (note that this related to unimplemented feature RIC-1007)
    22. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    23. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    24. RIC-915 dms_cli for installing xapp not working (raised by James)
    25. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    26. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    27. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    28. RIC-894 long idle period (days) causes RMR connection breaks
    29. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    30. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    31. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
    32. RIC-837 RMR is not forwarding messages from E2T to E2M
    33. RIC-835 → 2021-12-07 no news from Viktor
    34. fixed: 
  4. James: updates?
    1. 2023-11-21
      1. was at OSC-OAI conference
      2. could start using team accounts to test beds from Colosseum (NU) and ARA
      3. discussed with Bimo (Taiwan lab) on pair-wise testing
      4. discussed with John Keeney (non-rt ric ptl) and discussed A1 pairwise testing. Asked from Sunil what's best A1-policy using xApp. None exists on open-src side. Naman commented that for Policy the hello-world xApp (C++ likely) could be used (just requires RMR  route for policy type (must match the policy type that is created via curl)). James to contact Naman if help needed.
    2. 2024-01-16: TM-500 in Taiwan lab is again available (discussions with Intel on bringing up L1 and L2). RIC probably not one of the very next steps.
    3. 2023-01-30: O-RAN f-2-f: James asked if any demo planned. → not planned.
    4. 2024-02-13: thinking about demos for f-2-f (in discussion with Bimu)
    5. 2024-03-12: No updates. Willing to give demo on ORAN-SC Near RT RIC Demo. Details to be worked on the technical and demo content.
    6. 2024-03-26: Unavailable today.
    7. 2024-04-23:
    8. 2024-05-07: Updated on ORANSC summit. It was well received.
    9. 2024-05-21: No new updates this time.
  5. Prashant's work in near-RT RIC(subteam-p)
    1. 2023-08-22, 2023-09-26. 2023-11-07: could not participate
    2. 2024-02-13,2024-03-12,2024-03-26,2024-04-09,2024-04-23,2024-05-07, 2024-05-21: no news
  6. Sunil updates (subteam-h)?
    1. 2023-09-12: can give update next time. Maybe 2 or 3 items to work on.
    2. 2023-11-07: Not in the call today
    3. 2023-11-21: no updates. Difficult to find engineers working on this.
    4. 2024-01-16: demo of xApp project additions in I release → Next time
    5. 2024-01-16: re-evaluating RIC platform Jira items
    6. 2024-01-30: went through old Jira ticket, initial plan for release J: RIC-950, RIC-926, RIC-878 and RIC-860
    7. 2024-02-13: working on RIC subscription delete testing 
    8. 2024-03-12: Implementation completed, facing issues in code submission.
    9. 2024-03-26: Working on RIC-1049, documentation will also be made - Done
    10. 2024-03-09: Absent
    11. 2024-04-23: Not much updates.
    12. 2024-05-07: RIC-1045/RIC-1049 /RIC-1052/RIC-837 are completed. RIC-829 needs code commit.
    13. 2024-05-21:  unavailable
  7. Subhash/Naman updates (subteam-s) ?
    1. 2023-12-05: Naman gave an update on status of Samsung items
    2. 2024-01-16: Naman updated readme (still to merged) on how to deploy RIC using operators.
    3. 2024-01-30, 2024-02-13: no news, but still needs to work on RIC-1031
    4. 2024-03-12: RIC-1031 - Needs more time to complete, To start working on  A1 mediator integration with Non RealTime RIC
    5. 2024-03-26:  Continuing on RIC-1031, Working on RIC-1048 (analysis on RMR scaling, design to be worked upon)
    6. 2024-03-09,2024-04-23,2024-05-07,2024-05-21,2024-06-04: Not available
  8. Abhijit updates (subteam-ag) ?
    1. 2023-10-24:
      1. Abhijit and James release new base image: docker pull nexus3.o-ran-sc.org:10002/o-ran-sc/bldr-ubuntu22-c-go:0.1.0 → still to be made 1.0.0 → Reminder Abhijit Gadgil 
      2. no progress in review on the plain helm chart based deployment in https://gerrit.o-ran-sc.org/r/c/ric-plt/ric-dep/+/11743 → to be merged by Thoralf Czichy 
      3. 1 and 2 of RIC-1004 still be finailized this week. Rest to be moved to a new item.
      4. Sunil asked about the Rust xApp → ready with basic hello world scenario. Documentation is best placed into readme and  confluence.
    2. 2024-01-16, 2024-01-30: No news.
    3. 2024-02-13: continues work on xapp framework rust, incl. metric support
    4. 2024-03-12: No news.
    5. 2024-03-26: Implementation done , testing pending for xapp framework rust, incl. metric support
    6. 2024-03-09: Not available.
    7. 2024-03-23: Interested to work on 1056,1057 in coming weeks, after rust framework is tested. RIC-1006 done, RIC-1007 move to K, RIC-1028- will be taken up next. To give demo on rust-framework 07-05-2024.
    8. 2024-05-07:  RIC-1041 is done. Demo was given for metrics support in xapp-frame-rust that has default RMR Rx/Tx counters.
    9. Video for the demo added.
    10. 2024-05-21,2024-06-04: Unavailable
  9. Cap Gemini updates (subteam-cg)? 
    1. We agreed to come back to repo creation for phase 2 (ricapp part) of conflict manager in 1H2024
    2. 2024-01-16: Ashish presented the  design of conflict manager, first phase: link to slideset
    3. 2024-03-26,2024-03-09,2024-04-23,2024-05-07,2024-05-21,2024-06-04: unavailable.
  10. Himanshu (subteam-gs) would like to work on RIC-963
    1. 2023-12-05: RIC-963 seems to be ready. Himanshu still wants to test this with unordered IEs. Requires a minor addition in ric-dep repo for new config parameter.
    2. 2024-01-16: RIC-963 ready and merged. New review for RIC-1030 for final changes on checking (or not checking) IE order in additional messages.
    3. 2024-03-12:  Interested work in open issues that are already assigned. To check RIC-1047, if Dhiraj is not working,   length of IE > 1024 in RIC_ACTION_DEFINITION causing some issue. Sandeep is working in it. Issue in submgr. Good to raise JIRA.
    4. 2024-03-26: Assigned RIC-1043,1044,1047. Will provide updates next week.  length of IE > 1024 in RIC_ACTION_DEFINITION causing issue in submgr - Sandeep to check if Jira needs to be raised. RIC-1051- Himanshu looking into it.
    5. 2024-03-09:  No updates on RIC-1043,1044,1047. Amit will contribute to this project.
    6. 2024-04-23: Not present
    7. 2024-05-07: RIC-1044 code committed, to be merged.RIC-1047 WIP, issue not reproducible. Possible issue identified, but need to reproduce. e2sim has some dependency on ubuntu 18.04 version(gcc) Issue to be raised for this also. Another Issue : Himanshu to raise issue related to RIC-1052
    8. 2024-05-21: Issue with e2sim identified and corrected (SIM-117), Issue related to 1052 , additional steps added by Amit and now stands closed.
  11. Dhiraj:
    1. 2023-12-05: moved the IPv6 item  to J release
    2. 2024-01-16: approval for changes to be committed now obtained. IPv6-related commits expected over the next weeks.
    3. 2024-01-26, 2024-04-09,2024-04-23: no news.
    4. 2024-05-07: Dhiraj not representing Rakuten anymore.
    5. 2024-05-21,2024-06-04: Unavailable
  12. Alexandre (subteam-utfpr)
    1. 2023-08-29: Alexandre working on RIC-989 and RIC-991. Will also take a look at RIC-1001
    2. 2023-09-26: subscription message issue with encoding E2SM parts. A. will send e-mail to Thoralf
    3. 2024-03-12: RIC-989 and RIC-991 closed. RIC-1001 would need support from ric-plt/rtmgr, will send email to Abdulwahid. xapp-frame(C++) changes for xapp registration locally completed. Jira will be raised
    4. 2024-03-26,2024-04-09,2024-04-23: No news.
    5. 2024-05-07: Via mail responded to working on bug fixes in xapp-frame's. xapp-frame-cpp working well, still to make it work on xapp-frame(go) and xapp-frame-py
    6. 2024-05-21,2024-06-04: Unavailable
  13. Nokia (subteam-n)
    1. RIC-997 postponed to J
    2. 2024-02-13: Thoralf leaving Nokia/PTL role. Role is open for applications. Nokia nominated Abdulwahid.
  14. ORAN-SC half day workshop, San Jose, CA on April 29th - Any volunteers to make on-site demo of NEAR RT RIC - James will take it up.
    1. 2024-03-26: New nomination awaited from TOC.
    2. 2024-04-09: The presentation of NEAR RT RIC would be handled by someone else(not James)
    3. “Analysis of Opensource Near-RT RICs – A comparative study”. Mainly, Intern will take the Specs, and analyse the available opensources of Near-RT RICs and prepare a report. I wanted to know your thoughts and interest in mentoring this activity. 
  15. J release
    1. 2024-02-13: Naman's input
      1. no Jira tickets yet, but woudl like to focus on 
        1. K8S operator for day 2 operations, like scale-in and scale-out (but requires some thoughts on messaging) : RIC-1048
    2. I release theme for near-rt RIC was "RIC Platform Enhancements". What's it going to be for J?
      1. Thoralf's proposal based on current Jira list: "Make the platform more robust in handling E2AP, conflicts and A1"
    3. We mark items that you are >90% sure (=”committed”) to work on during 1H2024 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for J release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
      1. committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-p, subteam-s, subteam-utfpr, subteam-ag, subteam-cg, subteam-r, subteam-gs
      2. committed items only: all teams (committed) and all teams (committed + tentative).
      3. items that are known to require work, but are currently not in J release: link,  to include k8s version upgrade, ubuntu OS version, clean up of pending issues.
    1. input for release candidates: leftovers and generally open items, RSAC
    2. Sprint dates
      1. Sprint J release dev sprint 1: Feb-19 to Mar-10
      2. Sprint J release dev sprint 2: Mar-11 to Mar-31
      3. Sprint J release dev sprint 3: Apr-1 to Apr-21
      4. Sprint J release dev sprint 4: Apr-22 to May-12 (last planned development sprint)
      5. Sprint J release dev sprint 5: May-13 to Jun-2 (only for unplanned last-minute development items)
  16. RICAPP agenda: RICAPP Meetings.

2024-05-21

Recording:  zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on (end of I release)
      1. TODO
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2023-12-14 as part of release notes:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-1057 gNB unable to connect during high amount of Subscription Requests - Assigned to Amit Mishra - needs steps to reproduce this.
    2. RIC-1056 Crashing e2mgr after sending high amount of Subscription Requests - Assigned to Dhiraj
    3. RIC-1055 Unrestricted Registration of RMR Routing Information by xApp
    4. RIC-1054 Kong pod is in crash loopback due to Ingress controller container is not coming up in 1.28 k8s installation- mostly needs kongversion upgrade. Abhijit provided hints.
    5. RIC-1051 Problems with deploying xAPPs for the Near-RT RIC - RELEASE H&I - hwgo is gettong onboarded, still some issues with kpimon-go
    6. RIC-1047 crash in E2T metric increment code - WIP- Unable to reproduce the issue.
    7. RIC-1045 A1 mediator is in crash loopback state for H-Release And I-Release (HCL team can fix) → DONE (was a mismatch between ric-dep and image versions)
    8. RIC-1044 Potential Missing Array Size Checks Leading to Crashes in e2mgr  - code already committed. Wahid to check with Aditya for merging.
    9. RIC-1043 Crash in E2T buildPrometheusList Function  - WIP - Unable to reproduce the issue.
    10. RIC-1042 Can't register xApp
    11. RIC-1031 Data model is not compliant with latest A1 spec → Naman (planned to start work in next week)
    12. RIC-1032 → RIC-1035 - we continue with this under RIC-1035 (discussed with Abhijit in the project meeting) → Thoralf needs to take next step here (see also Abhijit's comment in RIC-1035 and in review)
    13. RIC-1025 memory leak in routing manager
    14. RIC-1017 xapp-frame -  xapp-frame may not be able to successfully subscribe to messages
    15. RIC-1016 e2t sctp_params structure may not be initialized properly → Nokia

    16. RIC-1015 e2t too High default message size. → Nokia

    17. RIC-1014 e2t potential race condition in the `listener` function due to multiple `listener` threads. → Nokia

    18. RIC-1013 e2t e2term pod does not become ready. Possible stack/heap corruption 

    19. RIC-1002 (Nokia fixes) Abnormal signaling process cause E2Term crash (this could be a security issue) → DONE
    20. RIC-1001 CVE-2023-41627 RMR service should verify route tables - Alexandre will take a look (note that this related to unimplemented feature RIC-1007)
    21. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    22. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    23. RIC-915 dms_cli for installing xapp not working (raised by James)
    24. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    25. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    26. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    27. RIC-894 long idle period (days) causes RMR connection breaks
    28. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    29. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    30. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
    31. RIC-837 RMR is not forwarding messages from E2T to E2M
    32. RIC-835 → 2021-12-07 no news from Viktor
    33. fixed: 
  4. James: updates?
    1. 2023-11-21
      1. was at OSC-OAI conference
      2. could start using team accounts to test beds from Colosseum (NU) and ARA
      3. discussed with Bimo (Taiwan lab) on pair-wise testing
      4. discussed with John Keeney (non-rt ric ptl) and discussed A1 pairwise testing. Asked from Sunil what's best A1-policy using xApp. None exists on open-src side. Naman commented that for Policy the hello-world xApp (C++ likely) could be used (just requires RMR  route for policy type (must match the policy type that is created via curl)). James to contact Naman if help needed.
    2. 2024-01-16: TM-500 in Taiwan lab is again available (discussions with Intel on bringing up L1 and L2). RIC probably not one of the very next steps.
    3. 2023-01-30: O-RAN f-2-f: James asked if any demo planned. → not planned.
    4. 2024-02-13: thinking about demos for f-2-f (in discussion with Bimu)
    5. 2024-03-12: No updates. Willing to give demo on ORAN-SC Near RT RIC Demo. Details to be worked on the technical and demo content.
    6. 2024-03-26: Unavailable today.
    7. 2024-04-23:
    8. 2024-05-07: Updated on ORANSC summit. It was well received.
    9. 2024-05-21: No new updates this time.
  5. Prashant's work in near-RT RIC(subteam-p)
    1. 2023-08-22, 2023-09-26. 2023-11-07: could not participate
    2. 2024-02-13,2024-03-12,2024-03-26,2024-04-09,2024-04-23,2024-05-07, 2024-05-21: no news
  6. Sunil updates (subteam-h)?
    1. 2023-09-12: can give update next time. Maybe 2 or 3 items to work on.
    2. 2023-11-07: Not in the call today
    3. 2023-11-21: no updates. Difficult to find engineers working on this.
    4. 2024-01-16: demo of xApp project additions in I release → Next time
    5. 2024-01-16: re-evaluating RIC platform Jira items
    6. 2024-01-30: went through old Jira ticket, initial plan for release J: RIC-950, RIC-926, RIC-878 and RIC-860
    7. 2024-02-13: working on RIC subscription delete testing 
    8. 2024-03-12: Implementation completed, facing issues in code submission.
    9. 2024-03-26: Working on RIC-1049, documentation will also be made - Done
    10. 2024-03-09: Absent
    11. 2024-04-23: Not much updates.
    12. 2024-05-07: RIC-1045/RIC-1049 /RIC-1052/RIC-837 are completed. RIC-829 needs code commit.
    13. 2024-05-21:  unavailable
  7. Subhash/Naman updates (subteam-s) ?
    1. 2023-12-05: Naman gave an update on status of Samsung items
    2. 2024-01-16: Naman updated readme (still to merged) on how to deploy RIC using operators.
    3. 2024-01-30, 2024-02-13: no news, but still needs to work on RIC-1031
    4. 2024-03-12: RIC-1031 - Needs more time to complete, To start working on  A1 mediator integration with Non RealTime RIC
    5. 2024-03-26:  Continuing on RIC-1031, Working on RIC-1048 (analysis on RMR scaling, design to be worked upon)
    6. 2024-03-09,2024-04-23,2024-05-07,2024-05-21: Not available
  8. Abhijit updates (subteam-ag) ?
    1. 2023-10-24:
      1. Abhijit and James release new base image: docker pull nexus3.o-ran-sc.org:10002/o-ran-sc/bldr-ubuntu22-c-go:0.1.0 → still to be made 1.0.0 → Reminder Abhijit Gadgil 
      2. no progress in review on the plain helm chart based deployment in https://gerrit.o-ran-sc.org/r/c/ric-plt/ric-dep/+/11743 → to be merged by Thoralf Czichy 
      3. 1 and 2 of RIC-1004 still be finailized this week. Rest to be moved to a new item.
      4. Sunil asked about the Rust xApp → ready with basic hello world scenario. Documentation is best placed into readme and  confluence.
    2. 2024-01-16, 2024-01-30: No news.
    3. 2024-02-13: continues work on xapp framework rust, incl. metric support
    4. 2024-03-12: No news.
    5. 2024-03-26: Implementation done , testing pending for xapp framework rust, incl. metric support
    6. 2024-03-09: Not available.
    7. 2024-03-23: Interested to work on 1056,1057 in coming weeks, after rust framework is tested. RIC-1006 done, RIC-1007 move to K, RIC-1028- will be taken up next. To give demo on rust-framework 07-05-2024.
    8. 2024-05-07:  RIC-1041 is done. Demo was given for metrics support in xapp-frame-rust that has default RMR Rx/Tx counters.
    9. Video for the demo added.
    10. 2024-05-21: Unavailable
  9. Cap Gemini updates (subteam-cg)? 
    1. We agreed to come back to repo creation for phase 2 (ricapp part) of conflict manager in 1H2024
    2. 2024-01-16: Ashish presented the  design of conflict manager, first phase: link to slideset
    3. 2024-03-26,2024-03-09,2024-04-23,2024-05-07,2024-05-21: unavailable.
  10. Himanshu (subteam-gs) would like to work on RIC-963
    1. 2023-12-05: RIC-963 seems to be ready. Himanshu still wants to test this with unordered IEs. Requires a minor addition in ric-dep repo for new config parameter.
    2. 2024-01-16: RIC-963 ready and merged. New review for RIC-1030 for final changes on checking (or not checking) IE order in additional messages.
    3. 2024-03-12:  Interested work in open issues that are already assigned. To check RIC-1047, if Dhiraj is not working,   length of IE > 1024 in RIC_ACTION_DEFINITION causing some issue. Sandeep is working in it. Issue in submgr. Good to raise JIRA.
    4. 2024-03-26: Assigned RIC-1043,1044,1047. Will provide updates next week.  length of IE > 1024 in RIC_ACTION_DEFINITION causing issue in submgr - Sandeep to check if Jira needs to be raised. RIC-1051- Himanshu looking into it.
    5. 2024-03-09:  No updates on RIC-1043,1044,1047. Amit will contribute to this project.
    6. 2024-04-23: Not present
    7. 2024-05-07: RIC-1044 code committed, to be merged.RIC-1047 WIP, issue not reproducible. Possible issue identified, but need to reproduce. e2sim has some dependency on ubuntu 18.04 version(gcc) Issue to be raised for this also. Another Issue : Himanshu to raise issue related to RIC-1052
    8. 2024-05-21: Issue with e2sim identified and corrected (SIM-117), Issue related to 1052 , additional steps added by Amit and now stands closed.
  11. Dhiraj:
    1. 2023-12-05: moved the IPv6 item  to J release
    2. 2024-01-16: approval for changes to be committed now obtained. IPv6-related commits expected over the next weeks.
    3. 2024-01-26, 2024-04-09,2024-04-23: no news.
    4. 2024-05-07: Dhiraj not representing Rakuten anymore.
    5. 2024-05-21: Unavailable
  12. Alexandre (subteam-utfpr)
    1. 2023-08-29: Alexandre working on RIC-989 and RIC-991. Will also take a look at RIC-1001
    2. 2023-09-26: subscription message issue with encoding E2SM parts. A. will send e-mail to Thoralf
    3. 2024-03-12: RIC-989 and RIC-991 closed. RIC-1001 would need support from ric-plt/rtmgr, will send email to Abdulwahid. xapp-frame(C++) changes for xapp registration locally completed. Jira will be raised
    4. 2024-03-26,2024-04-09,2024-04-23: No news.
    5. 2024-05-07: Via mail responded to working on bug fixes in xapp-frame's. xapp-frame-cpp working well, still to make it work on xapp-frame(go) and xapp-frame-py
    6. 2024-05-21: Unavailable
  13. Nokia (subteam-n)
    1. RIC-997 postponed to J
    2. 2024-02-13: Thoralf leaving Nokia/PTL role. Role is open for applications. Nokia nominated Abdulwahid.
  14. ORAN-SC half day workshop, San Jose, CA on April 29th - Any volunteers to make on-site demo of NEAR RT RIC - James will take it up.
    1. 2024-03-26: New nomination awaited from TOC.
    2. 2024-04-09: The presentation of NEAR RT RIC would be handled by someone else(not James)
    3. “Analysis of Opensource Near-RT RICs – A comparative study”. Mainly, Intern will take the Specs, and analyse the available opensources of Near-RT RICs and prepare a report. I wanted to know your thoughts and interest in mentoring this activity. 
  15. J release
    1. 2024-02-13: Naman's input
      1. no Jira tickets yet, but woudl like to focus on 
        1. K8S operator for day 2 operations, like scale-in and scale-out (but requires some thoughts on messaging) : RIC-1048
    2. I release theme for near-rt RIC was "RIC Platform Enhancements". What's it going to be for J?
      1. Thoralf's proposal based on current Jira list: "Make the platform more robust in handling E2AP, conflicts and A1"
    3. We mark items that you are >90% sure (=”committed”) to work on during 1H2024 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for J release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
      1. committed (90% sure) and tentative (90...30% sure) items: subteam-n, subteam-h, subteam-p, subteam-s, subteam-utfpr, subteam-ag, subteam-cg, subteam-r, subteam-gs
      2. committed items only: all teams (committed) and all teams (committed + tentative).
      3. items that are known to require work, but are currently not in J release: link,  to include k8s version upgrade, ubuntu OS version, clean up of pending issues.
    1. input for release candidates: leftovers and generally open items, RSAC
    2. Sprint dates
      1. Sprint J release dev sprint 1: Feb-19 to Mar-10
      2. Sprint J release dev sprint 2: Mar-11 to Mar-31
      3. Sprint J release dev sprint 3: Apr-1 to Apr-21
      4. Sprint J release dev sprint 4: Apr-22 to May-12 (last planned development sprint)
      5. Sprint J release dev sprint 5: May-13 to Jun-2 (only for unplanned last-minute development items)
  16. RICAPP agenda: RICAPP Meetings.

2024-05-07

Recording:  zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on (end of I release)
      1. TODO
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2023-12-14 as part of release notes:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-1057 gNB unable to connect during high amount of Subscription Requests
    2. RIC-1056 Crashing e2mgr after sending high amount of Subscription Requests
    3. RIC-1055 Unrestricted Registration of RMR Routing Information by xApp
    4. RIC-1054 Kong pod is in crash loopback due to Ingress controller container is not coming up in 1.28 k8s installation- mostly needs kongversion upgrade. Abhijit provided hints.
    5. RIC-1051 Problems with deploying xAPPs for the Near-RT RIC - RELEASE H&I - To be checked by Himanshu
    6. RIC-1047 crash in E2T metric increment code - WIP
    7. RIC-1045 A1 mediator is in crash loopback state for H-Release And I-Release (HCL team can fix) → DONE (was a mismatch between ric-dep and image versions)
    8. RIC-1044 Potential Missing Array Size Checks Leading to Crashes in e2mgr  
    9. RIC-1043 Crash in E2T buildPrometheusList Function  - WIP
    10. RIC-1042 Can't register xApp
    11. RIC-1031 Data model is not compliant with latest A1 spec → Naman (planned to start work in next week)
    12. RIC-1032 → RIC-1035 - we continue with this under RIC-1035 (discussed with Abhijit in the project meeting) → Thoralf needs to take next step here (see also Abhijit's comment in RIC-1035 and in review)
    13. RIC-1025 memory leak in routing manager
    14. RIC-1017 xapp-frame -  xapp-frame may not be able to successfully subscribe to messages
    15. RIC-1016 e2t sctp_params structure may not be initialized properly → Nokia

    16. RIC-1015 e2t too High default message size. → Nokia

    17. RIC-1014 e2t potential race condition in the `listener` function due to multiple `listener` threads. → Nokia

    18. RIC-1013 e2t e2term pod does not become ready. Possible stack/heap corruption 

    19. RIC-1002 (Nokia fixes) Abnormal signaling process cause E2Term crash (this could be a security issue) → DONE
    20. RIC-1001 CVE-2023-41627 RMR service should verify route tables - Alexandre will take a look (note that this related to unimplemented feature RIC-1007)
    21. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    22. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    23. RIC-915 dms_cli for installing xapp not working (raised by James)
    24. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    25. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    26. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    27. RIC-894 long idle period (days) causes RMR connection breaks
    28. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    29. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    30. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
    31. RIC-837 RMR is not forwarding messages from E2T to E2M
    32. RIC-835 → 2021-12-07 no news from Viktor
    33. fixed: 
  4. James: updates?
    1. 2023-11-21
      1. was at OSC-OAI conference
      2. could start using team accounts to test beds from Colosseum (NU) and ARA
      3. discussed with Bimo (Taiwan lab) on pair-wise testing
      4. discussed with John Keeney (non-rt ric ptl) and discussed A1 pairwise testing. Asked from Sunil what's best A1-policy using xApp. None exists on open-src side. Naman commented that for Policy the hello-world xApp (C++ likely) could be used (just requires RMR  route for policy type (must match the policy type that is created via curl)). James to contact Naman if help needed.
    2. 2024-01-16: TM-500 in Taiwan lab is again available (discussions with Intel on bringing up L1 and L2). RIC probably not one of the very next steps.
    3. 2023-01-30: O-RAN f-2-f: James asked if any demo planned. → not planned.
    4. 2024-02-13: thinking about demos for f-2-f (in discussion with Bimu)
    5. 2024-03-12: No updates. Willing to give demo on ORAN-SC Near RT RIC Demo. Details to be worked on the technical and demo content.
    6. 2024-03-26: Unavailable today.
    7. 2024-04-23:
    8. 2024-05-07: Updated on ORANSC summit. It was well received.
  5. Prashant's work in near-RT RIC(subteam-p)
    1. 2023-08-22, 2023-09-26. 2023-11-07: could not participate
    2. 2024-02-13,2024-03-12,2024-03-26,2024-04-09,2024-04-23,2024-05-07: no news
  6. Sunil updates (subteam-h)?
    1. 2023-09-12: can give update next time. Maybe 2 or 3 items to work on.
    2. 2023-11-07: Not in the call today
    3. 2023-11-21: no updates. Difficult to find engineers working on this.
    4. 2024-01-16: demo of xApp project additions in I release → Next time
    5. 2024-01-16: re-evaluating RIC platform Jira items
    6. 2024-01-30: went through old Jira ticket, initial plan for release J: RIC-950, RIC-926, RIC-878 and RIC-860
    7. 2024-02-13: working on RIC subscription delete testing 
    8. 2024-03-12: Implementation completed, facing issues in code submission.
    9. 2024-03-26: Working on RIC-1049, documentation will also be made - Done
    10. 2024-03-09: Absent
    11. 2024-04-23: Not much updates.
    12. 2024-05-07: RIC-1045/RIC-1049 /RIC-1052/RIC-837 are completed. RIC-829 needs code commit.
  7. Subhash/Naman updates (subteam-s) ?
    1. 2023-12-05: Naman gave an update on status of Samsung items
    2. 2024-01-16: Naman updated readme (still to merged) on how to deploy RIC using operators.
    3. 2024-01-30, 2024-02-13: no news, but still needs to work on RIC-1031
    4. 2024-03-12: RIC-1031 - Needs more time to complete, To start working on  A1 mediator integration with Non RealTime RIC
    5. 2024-03-26:  Continuing on RIC-1031, Working on RIC-1048 (analysis on RMR scaling, design to be worked upon)
    6. 2024-03-09,2024-04-23,2024-05-07: Not available
  8. Abhijit updates (subteam-ag) ?
    1. 2023-10-24:
      1. Abhijit and James release new base image: docker pull nexus3.o-ran-sc.org:10002/o-ran-sc/bldr-ubuntu22-c-go:0.1.0 → still to be made 1.0.0 → Reminder Abhijit Gadgil 
      2. no progress in review on the plain helm chart based deployment in https://gerrit.o-ran-sc.org/r/c/ric-plt/ric-dep/+/11743 → to be merged by Thoralf Czichy 
      3. 1 and 2 of RIC-1004 still be finailized this week. Rest to be moved to a new item.
      4. Sunil asked about the Rust xApp → ready with basic hello world scenario. Documentation is best placed into readme and  confluence.
    2. 2024-01-16, 2024-01-30: No news.
    3. 2024-02-13: continues work on xapp framework rust, incl. metric support
    4. 2024-03-12: No news.
    5. 2024-03-26: Implementation done , testing pending for xapp framework rust, incl. metric support
    6. 2024-03-09: Not available.
    7. 2024-03-23: Interested to work on 1056,1057 in coming weeks, after rust framework is tested. RIC-1006 done, RIC-1007 move to K, RIC-1028- will be taken up next. To give demo on rust-framework 07-05-2024.
    8. 2024-05-07:  RIC-1041 is done. Demo was given for metrics support in xapp-frame-rust that has default RMR Rx/Tx counters.
    9. Video for the demo added.
  9. Cap Gemini updates (subteam-cg)? 
    1. We agreed to come back to repo creation for phase 2 (ricapp part) of conflict manager in 1H2024
    2. 2024-01-16: Ashish presented the  design of conflict manager, first phase: link to slideset
    3. 2024-03-26,2024-03-09,2024-04-23,2024-05-07: unavailable.
  10. Himanshu (subteam-gs) would like to work on RIC-963
    1. 2023-12-05: RIC-963 seems to be ready. Himanshu still wants to test this with unordered IEs. Requires a minor addition in ric-dep repo for new config parameter.
    2. 2024-01-16: RIC-963 ready and merged. New review for RIC-1030 for final changes on checking (or not checking) IE order in additional messages.
    3. 2024-03-12:  Interested work in open issues that are already assigned. To check RIC-1047, if Dhiraj is not working,   length of IE > 1024 in RIC_ACTION_DEFINITION causing some issue. Sandeep is working in it. Issue in submgr. Good to raise JIRA.
    4. 2024-03-26: Assigned RIC-1043,1044,1047. Will provide updates next week.  length of IE > 1024 in RIC_ACTION_DEFINITION causing issue in submgr - Sandeep to check if Jira needs to be raised. RIC-1051- Himanshu looking into it.
    5. 2024-03-09:  No updates on RIC-1043,1044,1047. Amit will contribute to this project.
    6. 2024-04-23: Not present
    7. 2024-05-07: RIC-1044 code committed, to be merged.RIC-1047 WIP, issue not reproducible. Possible issue identified, but need to reproduce. e2sim has some dependency on ubuntu 18.04 version(gcc) Issue to be raised for this also. Another Issue : Himanshu to raise issue related to RIC-1052.
  11. Dhiraj (subteam-r)
    1. 2023-12-05: moved the IPv6 item  to J release
    2. 2024-01-16: approval for changes to be committed now obtained. IPv6-related commits expected over the next weeks.
    3. 2024-01-26, 2024-04-09,2024-04-23: no news.
    4. 2024-05-07: Dhiraj not representing Rakuten anymore.
  12. Alexandre (subteam-utfpr)
    1. 2023-08-29: Alexandre working on RIC-989 and RIC-991. Will also take a look at RIC-1001
    2. 2023-09-26: subscription message issue with encoding E2SM parts. A. will send e-mail to Thoralf
    3. 2024-03-12: RIC-989 and RIC-991 closed. RIC-1001 would need support from ric-plt/rtmgr, will send email to Abdulwahid. xapp-frame(C++) changes for xapp registration locally completed. Jira will be raised
    4. 2024-03-26,2024-04-09,2024-04-23: No news.
    5. 2024-05-07: Via mail responded to working on bug fixes in xapp-frame's. xapp-frame-cpp working well, still to make it work on xapp-frame(go) and xapp-frame-py
  13. Nokia (subteam-n)
    1. RIC-997 postponed to J
    2. 2024-02-13: Thoralf leaving Nokia/PTL role. Role is open for applications. Nokia nominated Abdulwahid.
  14. ORAN-SC half day workshop, San Jose, CA on April 29th - Any volunteers to make on-site demo of NEAR RT RIC - James will take it up.
    1. 2024-03-26: New nomination awaited from TOC.
    2. 2024-04-09: The presentation of NEAR RT RIC would be handled by someone else(not James)
    3. “Analysis of Opensource Near-RT RICs – A comparative study”. Mainly, Intern will take the Specs, and analyse the available opensources of Near-RT RICs and prepare a report. I wanted to know your thoughts and interest in mentoring this activity. 
  15. J release
    1. 2024-02-13: Naman's input
      1. no Jira tickets yet, but woudl like to focus on 
        1. K8S operator for day 2 operations, like scale-in and scale-out (but requires some thoughts on messaging) : RIC-1048
    2. I release theme for near-rt RIC was "RIC Platform Enhancements". What's it going to be for J?
      1. Thoralf's proposal based on current Jira list: "Make the platform more robust in handling E2AP, conflicts and A1"
    3. We mark items that you are >90% sure (=”committed”) to work on during 1H2024 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for J release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
      1. committed (90% sure) and tentative (90...30% sure) items: subteam-n,