2019-08-12 Meeting notes - Joint OAM / NONRTRIC SCRUM meeting
Date
Aug 12, 2019
Attendees
See also:
2019-08-12 Operations and Maintenance (OAM) Meeting notes
Discussion
Brief roundtable intro from participants who had not joined previous calls.
John: Update from NONRTRIC:
Gerrit repo https://gerrit.o-ran-sc.org/r/admin/repos/nonrtric and JIRA site https://jira.o-ran-sc.org/browse/NONRTRIC set up
Planning ongoing re candidates for NONRTRIC controller implementation - SDNC based component looking most favourable
Action: Need to coordinate with @Tommy Carpenter @Former user (Deleted) @John Keeney (Ericsson EST) about RIC dashboard & A1 mediation scope in NONRTRIC
Martin: Update from OAM
Facilities set up in OSC continuing ...
Jump straight into discussion on slides ... see next ...
Martin, All: Target/Reference architecture - Integration with ONAP - based on diagrams used in WG documents etc
Draft Slides
Focus on Slide 5 - clearest picture
Are we only using REST for A1? - Yes ... except maybe for A1-EI part - may use a streaming interface - no decision made yet.
Action: @John Keeney (Ericsson EST) Need a couple of sentences about why A1 uses REST on wiki
Should we split out constituent parts of A1? - Not yet ... perhaps wait until A1-EI is a bit clearer.
What is O1* interface .... ? Action @Martin Skorupski - David Kinsey is the best guy to ask.
May need to consider non-event-bus NBIs between components in the OAM space - In practice these non-event (e.g. REST, streaming etc) interfaces will be needed, but would just overly-complicate the diagram.
Does CDS etc need to be included. Or APPC etc? ... Probably. Will become clearer, esp when O1* interface is a bit clearer.
Tracy: Reminder about call for demos for ONS and MWC (others?).
Dongho: Have we plans/procedures in place for upstreaming changes back to ONAP? - Not yet. Discussion/Planning ongoing.
Good potential to engage with ONAP 5G usecases for ONAP Frankfurt - still time to engage with Frankfurt planning.
Action: Could @Tommy Carpenter @Former user (Deleted) please present a short update on the A1 parts of the NearRTRIC dashboard etc next week? - Yes.
Call cut short at T+58mniutes due to bridge reuse.
Action items