2020-05-11 Meeting notes - Joint OAM / NONRTRIC SCRUM meeting
NOTE: During the "Daylight Savings Time" changeover periods (US vs Europe vs Asia) the time of the meetings may fluctuate. Please keep an eye on the calendar on the Meetings page
Note about daylight savings time
Please note that the weekly OAM/NONRTRIC scrum team meeting will continue on Monday’s at 13:00 UTC.
Daylight Savings time changes have now completed for a few months so times are
6am PDT | 9am EDT | 13:00 UTC | 14:00 BST | 15:00 CEST | 16:00 EEST | 18:30 IST | 21:00 CST | 22:00 JST
See also:
Date
May 11, 2020
Attendees
@John Keeney (Ericsson EST)
@Martin Skorupski
@Alex Stancu
@Former user (Deleted)
@Sonia Sangari
@Eliza Celenti
@s.silvius
Sorry I didn't get a full attendance list for this meeting ... please add yourself ...
Discussion
NONRTRIC:
@John Keeney (Ericsson EST) brief discussion about topics that may form scope of Cherry plans. All TBC.
Enrichment Information
Evolution of A1-P specs from O-RAN Alliance WG2
Start gathering requirements and options for R-APPs, API & platform.
Alignment with ONAP in Guilin
@John Keeney (Ericsson EST) current tasks - prep for Bronze release planning
Improving DMaaP performance in A1 Policy Managment Service
Inter-working with OTF - help with VTH requirments and dev/test environment setup
Easy deployment
HTTPs & security certificate support (for all components)
IPv6 support
Ongoing testing & bug fixing (scaling, long-run tests, integration & function testing)
Documentation
Continuing to identify requirements for HealthCheck & TrafficSteering use cases.
@s.silvius Questions about what is meant by "external policy" on Traffic Steering wiki page
@John Keeney (Ericsson EST) That page needs to be tidies up - with John Ng & Gil Bullard
@s.silvius Onap Alignment is needed .....
OAM: (2020-05-11 OAM Meeting notes)
@Martin Skorupski Brief discussion on Cherry plans:
focus on modelling & leveraging existing functions already available in SMO.
Ongoing work on xApp modelling in WG1/WG3
OTF @Eliza Celenti:
Lack of resources remains a challenge - some delays getting resourcing up to speed.
VTHs are ready.
Scope reduced somewhat for Bronze eg. reduced scope in flows for Healthcheck use case
Will discuss Cherry planning in a follow up meetign
SIM
@Alex Stancu SIM/OAM - IPv6 demo -
Started recording (Springt 4 demo for SIM team)
Demo recording available