Date
Attendees
- John Keeney (Ericsson EST)
- Martin Skorupski
- Alex Stancu
- Konrad Bańka
- Lathishbabu Ganesan
- Sonia Sangari
- Pawel Slowikowski
- Subash (Samsung)
- Former user (Deleted)
- Sandeep Shah
- ksinghn247
- Changlan Tsai
- Some people may have joined later ... please add yourself ...
Notes:
NONRTRIC
ONAP upstreaming A1 Controler & A1 Policy Management Service (CCSDK)
- M4 rapidly approaching - still trying to get throught OOM and Cert management procedures
- Pawel Slowikowski would like to help - John Keeney (Ericsson EST) to send some JIRA links where help would be very welcome
- Working through an issue with Sonar score appearing too low ...
- M4 rapidly approaching - still trying to get throught OOM and Cert management procedures
- OSC Plans/Started for Cherry:
- May be able to re-add initial Enrichment Information coordination if WG2 makes progress in short-term
- RSAC: Cherry rqmnt for an Initial rApp catalogue/registry
- Overlaps with ongoing work in ONAP - may be able to reuse
- Clamp/Control-Loop & DCAE-Mod
- Overlaps with ongoing work in ONAP - may be able to reuse
- Downstreaming A1 Policy controller functions from ONAP
- Documentation changes due to updates above
- Need significant help here please
- A1 v2.0 update needed in all components
- A1 Policy notification support
- Changes to deployment options e.g. OOM - depends on SMO project
- Ongoing uncertainty over SMO project
- Once new PTL elected we will need to discuss scope overlap (also including OAM, INT etc)
OAM
- See 2020-08-31 OAM Meeting notes
- Dashboard/Portal update (from Lorraine A. Welch ): Working through JIRAs - all undercontrol
- John Keeney (Ericsson EST) Need to touch base re Non-RT-RIC Control Panel ... may need more alignment as more functions added - esp when support for Enrichment Information and Policy Notifications are added
- Some issues with authentication failing (regression test)... fix & further investigation ongoing
- Continuing to struggle with copyright uncertainty - liaising with TOC
SIM
- See 2020-08-31 SIM Meeting notes
- E2 Sim: Ongoing - awaiting update from Ron
- O1 Sim:
- Netconf upgrade
- ORAN Yang can now be used
- Provides a VES enpoint