2021-10-19 meeting agenda and minutes
Status update for EPICs in E release
- [INF-193] INF Implement the O2 interface as the MVP
- 5 sub-tasks:
- 2 done
- 2 in-progress
- 1 net started
- New repo is created: https://gerrit.o-ran-sc.org/r/admin/repos/pti/o2
- Bin: working on HLD
- 5 sub-tasks:
- [INF-173] INF Enable the multiple deployment scenarios: AIO-DX + workers
- Added 3 sub-tasks:
- 2 done: AIO-SX and AIO-DX
- 1 just started: AIO-DX with additional worker nodes
- New story is created in starlingx: [MultiOS][Yocto] enable AIO-DX + worker nodes | StoryBoard (openstack.org)
- Added 3 sub-tasks:
- [INF-215] INF fully align with StarlingX 5.0 to support the Container/Kubernetes platform
- 8 sub-tasks: All done
- Upstream Status for meta-starlingx on opendev:
- 156 commits
- 156 merged